"BOSTON — Massachusetts environmental regulators have denied a request by the company dismantling a shuttered nuclear power plant to release more than 1 million gallons (3.8 million liters) of radioactive wastewater into Cape Cod Bay.
The state Department of Environmental Protection’s draft decision issued Monday said it denied Holtec’s request for a permit modification because the discharge from Pilgrim Nuclear Power Station in Plymouth would violate a state law that designates the bay as an ocean sanctuary.
The draft will not be finalized until after a public comment period that ends Aug. 25."
Source: AP, 07/26/2023